Small Clean Energy Infrastructure Permitting and Zoning
Latest Update
Text Amendment No. 502 Article 88: Battery Energy Storage Systems and Consolidated Local Permit is effective as of September 14, 2026. On October 1, 2026, per 225 CMR 29.00 applicants may opt-into the Consolidated Local Permit process using the Department of Energy Resource’s online portal for application submission.
Comments and questions are welcome, and staff will continue to accept comments on the zoning on an ongoing basis. Questions related to the new zoning for Small Clean Energy Infrastructure Facilities can be submitted to: [email protected]
Overview
The City of Boston’s permitting process and zoning amendments for Small Clean Energy Infrastructure are effective as of September 14, 2026. This initiative aligns with the City’s and the Commonwealth’s broader climate goals to achieve net zero carbon emissions by 2050, increase resilience, and modernize the electrical grid.
The 2024 Act Promoting a Clean Energy Grid, Advancing Equity, and Protecting Ratepayers (“2024 Climate Act” or the"Act”) required the City of Boston to adopt a Consolidated Permit Pathway for Small Energy Infrastructure (CMR 29.00) to achieve our emissions goals. This optional pathway for developers abides by the new Consolidated Permit Pathway (CMR 29.00) beginning October 1, 2026.
Note: Large Clean Energy Infrastructure Projects (e.g. Substations and Battery Energy Storage over 100 MWh) are subject to State Energy Facilities Siting Board (EFSB) review and approval.
Adopted Zoning Changes
The zoning amendments comply with CMR 29.00, creating a clear, regulated framework for small clean energy projects to meet climate resilience goals:
-
Consolidated Local Permit Process: As required by CMR 29.00, this path establishes standard conditions, criteria, and procedures for the efficient siting and permitting of small-scale clean energy projects. Under this pathway, a final permit decision must be issued within one year. All projects that meet the State’s definition for Small Clean Energy Infrastructure Facilities are able to opt-in to this permitting process.
Small Clean Infrastructure Types
The following types and scales of Small Clean Energy Infrastructure are able to apply for a Consolidated Local Permit under this new zoning amendment:
-
BESS: Storage capacity less than 100 MWh. Required for BESS with a Site Footprint greater than 400 sq ft..
-
Solar Installations: Generation capacity less than 25 MW.
-
Anaerobic Digestion Facilities: Less than 25 MW.
-
Wind Facilities: Less than 25 MW.
-
Transmission & Distribution:
Next Steps
The Planning Department is currently drafting design guidelines for BESS in collaboration with other key City departments. These guidelines will complement the newly adopted zoning for BESS and will incorporate feedback that we have received through the zoning drafting process.
Past updates
The draft zoning was released prior to the virtual public meeting on Wednesday, July 29. In order to comply with the state deadline of October 1, 2026, this zoning was considered for approval by the BPDA Board on August 13, 2026 and the Zoning Commission on September 9, 2026.
Timeline

Engagement
Click on the event date to view details and materials.
Draft Zoning Release Virtual Meeting
Information Session