Pier 4 Fender Repairs, Charlestown Navy Yard

Stats

Last Updated 08/29/2013
Rss
  • Address:

    Charlestown Navy Yard

  • Neighborhood:

    Charlestown

  • Type:

    Pier Construction

  • Mass General Law:

    30

  • Owner:

    Boston Redevelopment Authority

  • Consultant:

    Childs Engineering Corporation

  • Contractor:

    RDA Construction Corp.

  • Estimate:

    120,000

Description:

Work generally consists of the demolition, removal and replacement of existing timber pile and fender system. Fourteen (14) existing creosote-treated timber fender piles will be removed and replaced with new chromated copper arsenate-treated timber piles. 100 linear feet of lower wale and 100 linear feet of upper wale systems will also be replaced.